Fédération Internationale Des Ingénieurs-Conseils

1.1 测量方法

12.2 Method of Measurement

除非合同中另有规定,无论当地惯例如何:

Except as otherwise stated in the Contract and notwithstanding local practice:

(a) 测量应该是测量每部分永久工程的实际净值,以及

(a) measurement shall be made of the net actual quantity of each item of the

Permanent Works, and

(b) 测量方法应符合工程量表或其他适用报表。

(b) the method of measurement shall be in accordance with the Bill of

Quantities or other applicable Schedules.

1.2 估价

12.3 Evaluation

除非合同中另有规定,工程师应通过对每一项工作的估价,根据第3.5款【决定】,商定

或决定合同价格。每项工作的估价是用依据上述第12.1款和第12.2款商定或决定的测量

数据乘以此项工作的相应价格费率或价格得到的。

Except as otherwise stated in the Contract, the Engineer shall proceed in

accordance with Sub-Clause 3.5 [Determinations] to agree or determine the

Contract Price by evaluating each item of work, applying the measurement

agreed or determined in accordance with the above Sub-Clauses 12.1 and 12.2

and the appropriate rate or price for the item.

对每一项工作,该项合适的费率或价格应该是合同中对此项工作规定的费率或价格,或

者如果没有该项,则为对其类似工作所规定的费率或价格。但是在下列情况下,对这一项工

作规定新的费率或价格将是合适的:

For each item of work, the appropriate rate or price for the item shall be the

rate or price specified for such item in the Contract or, if there is no such item,

specified for similar work. However, a new rate or price shall be appropriate for

an item of work if: (a) (i) 如果此项工作实际测量的工程量比工程量表或其他报表中规定

的工程量的变动大于10%;

(i)the measured quantity of the item is changed by ore than 10% from the

quantity of this item in the Bill of Quantities or other Schedule,